The refurb group visiting the building site

Before Christmas the referb group managed to get in the building site and we had lots of fun ! When we went in there is lots of awsome gadgets and lots of pipes and wires.

Things To Be Done By The Easter Holidays!

Zone A to be finished by the 12th of February. There will be a new ceiling and new windows fitted, the doors will be here soon.

Modular unit is completed inside and the corridor to join to school will be completed by spring term break.

New drainage and water pipes have been fitted. New sink area for P5/6 fitted by spring term break.

The new toilets are hoping to be fitted by Easter break (they had to start from scratch!).

The library will be back as a library at some point but they don't know when.

A new path going in at the back of the school starting within the next month. There will still be access to the old paths at all times.

Moving Classes

Thursday 18th of February p1s/p1g move to block A.

29th of February or fst March is when  p7 swap classes.

On Tuesday 23rd of Februrary p5/6 and p6 are moving into some decant rooms.

Changes

Modular classrooms won't be ready untill thecorridor doors are fitted.

The corridor doors should be arriving on the 22nd of February.

Primary 1, 5/6 and 6 were meant to be moving this week but have been held up so are hopefully moving next week instead. P7 are looking forward to moving in a few weeks!!!

MUGA Pitch

The planning consent has been given.

We are waiting final costings but they should be with us very shortly.

The proposed start date is the 21st of March. 

It is estimated to take 10 weeks to complete.